A Turkish Company Will Build Solar Power Plants Near Bugojno for 52.56 Million KM - Akta.ba Vijesti
5 Articles
5 Articles
The contract for the Gračanica 1 and Gračanica 2 solar power plants was signed by Elektroprivreda BiH with the Turkish company Girişim Elektrik from Ankara on September 10, 2026. The value of the contract is 26.87 million euros, or about 52.6 million KM.
On the land of the former coal mine near Bugojn, it is planned to build two solar power plants with a total capacity of at least 50 MWp, as part of the Elektroprivrede BiH project worth about 52,6 million KM. Elektroprivreda BiH has signed a contract with the Turkish company Girişim Elektrik from Ankara for the construction of two solar power plants Gračanica 1 and Gračanica 2 in the Bugojno municipality. The value [...] The post Turks sign cont…
Two solar power plants that Elektroprivreda BiH plans to build on former mining land near Bugojno have been granted a contract deadline. According to the contract award notice published by the European Bank for Reconstruction and Development (EBRD) on November 17, the planned completion date of the contract is May 31, 2031. The contract for the Gračanica 1 and Gračanica 2 solar power plants Elektroprivreda BiH [...]
The construction of the Gračanica 1 and 2 solar power plants with a total capacity of 50 MWp has been entrusted to the Turkish company Girisim Elektrik, with which Elektroprivreda BiH signed the contract on September 10, and the works should be completed by May 31, 2031.
Turkish Girişim Elektrik is building the Gračanica 1 and 2 solar power plants, and IPSA-RADIS is supervising the works. The two contracts of Elektroprivreda BiH are worth 53.04 million KM.
Coverage Details
Bias Distribution
- There is no tracked Bias information for the sources covering this story.
Factuality
To view factuality data please Upgrade to Premium