Fresh Ha Belo headache

Summary by Lesotho Times
…as High Court nullifies govt’s decision to fire Phaks JV from M170 million project …putting in limbo decision to appoint new company to take over project Mohloai Mpesi THE government finds itself in a bind after the High Court nullified its decision to terminate a M170 million contract with Phaks Joint Venture (Phaks JV), the company initially contracted to construct the long delayed Ha Belo electricity substation. The High Court decision is a …